What we're doing, when the work will start.

Where we're doing the work

We're delivering a scheme at:

  • Park Row
  • Perry Road
  • Upper Maudlin Street
  • Colston Street

What we're doing

Improvements include:

  • upgrading cycle lanes and other cycle infrastructure
  • upgrading crossings and other pedestrian infrastructure
  • upgrading traffic signals
  • creating loading and disabled bays

The work will:

  • make it easier and safer to walk and cycle
  • manage traffic flow and reduce pollution
  • encourage more sustainable travel in the area

We made the following changes to the scheme, based on feedback during the community engagement:  

  • installing no entry signage at Lower Church Lane
  • new loading bays on Perry Road and Upper Maudlin Street
  • removing 2 bus stops on Park Row and Perry Road, as services have been discontinued
  • simplifying cycle infrastructure at Woodland Road
  • installing more resilient cycle lane bollards

Programme of work

Construction will start in late March 2024 and is due to be completed by early 2025. It will include:

  • Park Row and Park Street junction: estimated start late March 2024, estimated finish late June 2024
  • Upper Maudlin Street and Lower Maudlin Street junction: estimated start early April 2024, estimated finish late May 2024
  • Park Row and Woodland Road junction: estimated start early April 2024, estimated finish mid-July 2024
  • Upper Maudlin Street from BRI Entrance to Lower Maudlin Street: estimated start late April 2024, estimated finish early January 2025
  • Perry Road and St Michael's Hill junction: estimated start late June 2024, estimated finish early January 2025
  • Lower Park Row and Colston Street junction: estimated start early July 2024, estimated finish mid-September 2024
  • Lower Park Row and Park Row junction: estimated start late September 2024, estimated finish mid-December 2024
  • Marlborough Street: estimated start early December 2024, estimated finish early January 2025

These dates are indicative and could change. This might be as a result of bad weather or unforeseen ground conditions. We will update this page as the works progress.

Some works, particularly those being carried out by third parties, could be carried out in isolation. The road resurfacing programme is yet to be confirmed.

Impact of works

Two-way traffic will be maintained as much as possible throughout the works, but one-way single lane traffic will be required during some off-peak periods.

Diversions will be put in place when road closures are required.

Planned closures (dates are indicative and could change):

Whitson Street

  • Between Marlborough Street and Earl Street throughout the works.

St Michaels Hill

  • Closed to northbound traffic from the junction with Perry Road and Upper Maudlin Street to Horfield Road from mid-July until early January

Lower Church Lane

  • Closed from the junction with Old Park Hill to St Michaels Hill from mid-July until early January

Colston Street

  • Closed between the Upper Maudlin Street and Lower Park Row junctions for one week in late July
  • Permanently closed to northbound traffic between Lower Park Row and Upper Maudlin Street from late July
  • Closed at the junction with Lower Park Row for one week in early October

Lower Park Row

  • Closed at the junction with Park Row from mid-October
  • Permanently closed to southbound traffic from the junction with Park Row from mid-October

Various locations

  • Roads will be closed during re-surfacing works: dates and locations to be confirmed

Access to businesses will be maintained at all times during working hours.

More information

If you have any questions about the works, contact the council's contractors, Taylor Woodrow, by emailing swbristol@taylorwoodrow.com

Thank you for your patience while we carry out these important improvement works.

This project forms part of the Department for Transport's Active Travel programme.